Heat pump regulations in Luxembourg in 2026: noise limits, permits and legal obligations

Before installing a heat pump in Luxembourg, you need to comply with several sets of rules: strict noise standards, municipal authorisations, the F-gas rules on refrigerants, mandatory installer certifications and planning compliance. This in-depth guide explains every legal requirement currently in force in Luxembourg so that your heat pump is installed fully in line with the rules.

📊 Key figures at a glance
  • Noise: there is no national noise limit specific to heat pumps; the model municipal building regulation, if the municipality has adopted it, sets 40 dB(A) (LAeq over 1 h) at the boundary of the nearest neighbouring building plot, +5 dB for tonal or impulsive noise.
  • Distance: under the 2023 model regulation, the outdoor unit of an air-to-water heat pump must be at least 2 m from the property boundary, with an exemption possible on an expert’s certificate.
  • Municipal authorisation: there is no general statutory deadline; if there is no reply within 3 months, the application can be deemed refused (the one-month deadline for heat pumps only appears in bill No. 8480, which has not yet been passed).
  • Co-ownership: a unit on the shared façade or roof, or one that alters the building’s external appearance, requires a general meeting vote by a majority of the votes of all co-owners (Art. 16 of the law of 16 May 1975).
  • Refrigerants: only an F-gas certified installer may charge the circuit; from 1 January 2027, a new air-to-water heat pump of 12 kW or less, monobloc or split, must use a refrigerant with a GWP below 150 (unless safety requirements dictate otherwise): R32 is no longer possible.
  • Inspection: under the law of 17 August 2026, an air-to-water or ground-source heat pump is inspected 1 to 2 years after commissioning, then every 4 years.

Need a compliance check?

Make sure your heat pump project meets every standard:


Heat pump noise standards and noise limits in Luxembourg

Noise is one of the main regulatory concerns with heat pumps. In Luxembourg there is no national noise limit specific to heat pumps: it is your municipality’s regulations that apply. The model building regulation (règlement-type sur les bâtisses), if your municipality has adopted it, sets a limit of 40 dB(A) (LAeq over 1 h) at the boundary of the nearest neighbouring building plot, which you can check with the schallrechner.lu calculator.

Statutory noise limits

Rule Limit in dB(A) Conditions
Model municipal building regulation (if your municipality has adopted it) 40 dB(A) (LAeq over 1 h) At the boundary of the nearest neighbouring building plot; +5 dB for tonal or impulsive noise; schallrechner.lu calculator
Klimabonus (air-to-water heat pump) ≤ 48 / 51 / 55 dB(A) sound power level Outdoor unit ≤ 5 kW / 5–12 kW / ≥ 12 kW, or ≤ 40 dB(A) at the neighbouring plot boundary
Other cases No national limit specific to heat pumps Depends on your municipality’s regulations (municipal police by-law on neighbourhood noise)

Specific heat pump requirements

  • Measurement point: at the boundary of the nearest neighbouring building plot (model municipal regulation)
  • Assessment period: average level over 1 hour (LAeq,1h), plus 5 dB for tonal or impulsive noise
  • Measurement standard: in line with ISO 3744 or 3746
  • Certificate required: for air-to-air heat pumps, an acoustic study is recommended if the distance is < 3 m

Standard EN 12102-1 defines how the airborne noise of heat pumps (sound power level) is measured: manufacturers declare the sound power of the outdoor unit according to this standard. The acoustic study report must include the exact position of the heat pump, the layout plans and an analysis of how noise is transmitted to neighbouring properties.

Typical heat pump noise levels

  • Average air-to-air heat pump: 38–42 dB(A) at 1 m (outdoor unit)
  • ‘Low-noise’ air-to-air heat pump: 32–38 dB(A) at 1 m
  • Ground-source heat pump: 30–35 dB(A) (quieter, no fan noise)
  • Gas boiler (for reference): 55–60 dB(A)

How to reduce heat pump noise

Measure Noise reduction Approx. cost
Anti-vibration mounts (rubber feet) 3–5 dB(A) €100–300
Acoustic screen (small) 5–8 dB(A) €400–900
Full acoustic enclosure 8–12 dB(A) €1,200–2,500
Pipe insulation (foam) 2–4 dB(A) €150–400
Choosing a ‘low-noise’ heat pump 4–8 dB(A) less than a standard model 15–25% extra cost
Tip

To stay within the model regulation’s 40 dB(A) limit at the neighbouring plot boundary, check your project with the schallrechner.lu calculator. Look for certified ‘low-noise’ models. A prior acoustic study (€500–800) saves you the far higher cost of bringing the installation into compliance later on.

Municipal authorisations and planning rules

Depending on the municipality and the type of installation, a building permit or a declaration of works may be required.

When do you need a permit?

Situation Required procedure
Air-to-air heat pump — private balcony — no structural alterations ✓ Often no formalities (depending on the municipality)
Outdoor unit on a visible façade — hole through a wall — installation in a co-owned building (common property) ⚠ Declaration of works required
Major structural alterations — collective heat pump installation ✗ Full building permit (rare)

Procedure with the municipality

  1. Step 1: contact your local town hall or planning department
  2. Step 2: ask whether a permit or declaration is required (include plans and the dimensions of the outdoor unit)
  3. Step 3: if so, submit an application with accurate plans, the installer’s quote and the technical specifications
  4. Step 4: time to decision: there is no general statutory deadline; if there is no reply within 3 months, the application can be deemed refused (implicit refusal). The one-month deadline for heat pumps is set out in bill No. 8480, which has not yet been passed
  5. Step 5: once you have written approval, keep a copy and start the work

Documents to prepare for the municipality: administrative form (provided by the town hall), cadastral plan showing the exact position of the outdoor unit (minimum scale 1:500), photographs of the site as it is now, technical drawings of the heat pump with exact dimensions and distances to the property boundaries, installer’s quote stating the heat pump model, installer’s public liability insurance certificate, and an acoustic study if the unit is < 3 m from neighbouring homes.

Warning

Do NOT start work without the municipality’s written approval. You risk being forced to bring the installation into compliance, fines and possibly having to remove the installation at your own expense.

Mandatory declaration to the Chambre des Métiers

Every heat pump installation must be declared to the Chambre des Métiers du Luxembourg (Chamber of Skilled Trades and Crafts) by your professional installer. The Chambre des Métiers then carries out a commissioning inspection of the installation to check that it meets technical and safety requirements.

Role of the Chambre des Métiers du Luxembourg

  • Registration: businesses must be registered before they can legally install a heat pump
  • Technical inspection: installations are inspected to check that they comply with safety and performance standards
  • Mandatory training: all installers must complete approved training courses that cover heat pumps
  • Certification: professional qualifications; F-gas certification for businesses is issued by the Environment Agency (AEV)
  • Quality monitoring: random site inspections may be carried out to check compliance

Installation certificate

After installation and a successful inspection, the installer issues an installation certificate stating: the heat pump’s serial number, the quantity of refrigerant charged (in kg and in tonnes of CO₂ equivalent), the date and signature of the certified installer, a statement of compliance with the F-gas rules, the leak test results, the certified SCOP/SEER performance data sheet and the Chambre des Métiers declaration number.

Important

Keep the installation certificate and the Chambre des Métiers declaration number for at least 10 years. The certificate proves that your installation is legally compliant, makes future maintenance easier and may be requested when you sell the property. Pass a copy on to the next owner.

F-gas regulations for heat pump refrigerants

Heat pumps contain a refrigerant classed as an F-gas (fluorinated gas), the use of which is strictly regulated. In Luxembourg, the rules are based on the F-gas Regulation (EU) 2024/573, in force since 11 March 2024, which replaces Regulation (EU) No 517/2014 and speeds up the phase-out of fluorinated greenhouse gases.

Regulatory context in 2026

  • From 1 January 2026: ban on using virgin F-gases with a GWP of 2,500 or more to service air-conditioning and heat pump equipment (reclaimed or recycled gas allowed until 2032; R410A, GWP 2,088, is not affected)
  • Phase-down quota: F-gas quota cut to 42.9 million tonnes CO₂-eq for 2025–2026
  • From 1 January 2027: new air-to-water heat pumps of 12 kW or less, monobloc or split: refrigerant GWP below 150 (unless safety requirements dictate otherwise); from 2032, no fluorinated gas at all in monoblocs of 12 kW or less
  • Splits ≤ 12 kW: since 1 January 2025, no new split systems containing less than 3 kg with a GWP ≥ 750 (which rules out R410A); from 1 January 2029, air-to-air splits with a GWP ≥ 150 are banned (the end of R32); from 1 January 2035, no fluorinated gases at all
Impact in 2026

If your current heat pump runs on R410A (GWP 2,088), it remains legal to operate as normal. It can also still be serviced and topped up: since 1 January 2026, Regulation (EU) 2024/573 has only banned servicing with virgin refrigerants with a GWP of 2,500 or more, and R410A (GWP 2,088) is below that threshold. The HFC quota phase-down will, however, make this refrigerant scarcer and more expensive. When you replace it, R32 is no longer possible for an air-to-water heat pump of 12 kW or less placed on the market from 2027: see R290 or R32 by brand.

Permitted and recommended refrigerants (2026)

Refrigerant Type GWP Status in 2026 Properties
R32 HFC 675 ✓ Permitted (new equipment: air-to-water ≤ 12 kW until the end of 2026, air-to-air split ≤ 12 kW until the end of 2028) A good compromise between environmental impact and performance. Mildly flammable (A2L). Industry standard for the new generation.
R410A HFC 2,088 ⚠ Excluded from new splits since 2025 Widely used in older heat pumps. High GWP. No longer permitted in new splits containing less than 3 kg since 1 January 2025.
R290 (propane) HC 3 ✓ Optimal — the future Minimal GWP, natural. Flammable (A3). Excellent performance. Slightly higher cost. Premium brands.
R600a (isobutane) HC 3 ✓ Optimal — the future Minimal GWP, natural hydrocarbon. Excellent performance. Flammable (A3). Growing uptake.
HFO-1234ze / HFO-1234yf HFO 1–7 ✓ Permitted Low-GWP synthetic gases (3rd generation). Mildly flammable (A2L). Still in development. Premium cost.

F-gas legal obligations

Obligation Heat pump < 5 t CO₂-eq Heat pump ≥ 5 t CO₂-eq
Periodic inspection (air-to-water or ground-source heat pump, law of 17 August 2026) ✗ 1 to 2 years after commissioning, then every 4 years ✗ 1 to 2 years after commissioning, then every 4 years
Leak check (fluorinated gases) ✓ Not required ✗ Every 12 months (24 months with a leak detection system)
Service report ⚠ Recommended ✗ Mandatory, documented
Maintenance log ⚠ Advisable ✗ Must be kept up to date
F-gas certified installer ✗ Required ✗ Required
Tip for a future-proof, compliant heat pump

For a new installation, choose a heat pump that runs on the natural refrigerants R290/R600a (the long-term future); R32 remains a good interim option where it is still permitted (new air-to-water units ≤ 12 kW until the end of 2026, air-to-air splits ≤ 12 kW until the end of 2028). Avoid R410A, which is being phased out. This keeps you in line with the latest rules and makes your investment future-proof.

Mandatory installer certifications and qualifications

Only a certified installer can legally install a heat pump in Luxembourg. The Chambre des Métiers du Luxembourg imposes a strict framework of training and qualifications.

Required certifications (mandatory)

1. Registration with the Chambre des Métiers Mandatory registration as a heating/air-conditioning installation business. You can check this on www.cdm.lu, under ‘Contrôle des installations du bâtiment’ (building services inspection).
2. F-gas certification (Category I or II) Mandatory for handling refrigerants (charging, maintenance, recovery). Theory training + approved exam (~2 days). Cat. I: all activities on all equipment; Cat. II: installation, servicing and recovery on equipment containing less than 3 kg of refrigerant (less than 6 kg if hermetically sealed), and leak checks without breaking into the refrigerant circuit (Implementing Regulation (EU) 2015/2067).
3. Public liability insurance Minimum cover of €500,000 for damage. An up-to-date insurance certificate is required before the contract is signed. Covers liability for injury to people or damage to property.
4. Chambre des Métiers inspections and checks The Chambre des Métiers may carry out random site inspections to check compliance. Installers are subject to compliance audits.
5. Manufacturer technical training (recommended) Heat pump manufacturer certification (Daikin, Mitsubishi, LG, etc.) for model-specific expertise. Optional, but it adds credibility and technical competence.

Essential checks before signing the contract

Certification What to check Risk if missing
Chambre des Métiers registration Registration number. Check it on www.cdm.lu Illegal, uninsured installation, no consumer rights
F-gas certification Copy of a valid F-gas certificate. Check the expiry date Refrigerant cannot be charged legally. Heat pump will not work, work invalid
Public liability insurance Current insurance certificate (minimum €500k). Expiry date If something goes wrong, you bear the cost of the damage. No recourse
Company registration Proof that the business is registered, VAT number where applicable Undeclared (cash-in-hand) work, no proper invoice, tax problems
References 2–3 recent customer references. Contact them if possible No reliable track record, questionable experience

To check that an installer is approved, go to www.cdm.lu, section ‘Contrôle des installations du bâtiment / installateurs’, enter the company name or registration number and check that the status shows ‘actif’ (active). You can also contact the Chambre des Métiers directly: Tel. +352 42 67 67 — [email protected]

Be extremely careful

Turn down any installer without valid Chambre des Métiers and F-gas certifications. The risks: a non-compliant installation, refrigerant charged illegally, no warranty, no liability cover and fines. Always ask for written proof before committing to anything.

Heat pump technical standards and performance

Every heat pump installed in Luxembourg must meet strict technical standards for energy efficiency, safety and performance. These standards are harmonised at European level through EU directives and supplemented by national regulations.

Applicable technical standards

Standard Scope Description
EN 14825 Seasonal performance Assessment of SCOP (heating) and SEER (cooling) under real climate conditions. Replaces the old instantaneous COP values.
EN 12102-1 Noise emissions Measurement of the sound power level of heat pumps (the value declared by the manufacturer), under standardised conditions.
EN 378 Refrigerating systems Safety of refrigerating systems (pressure, tightness, ventilation). Prevention of F-gas leaks.
Directive 2014/30/EU Electromagnetic compatibility Reduces electromagnetic interference. Ensures the heat pump does not disrupt nearby electrical appliances.
EPBD (Directive (EU) 2024/1275) Energy performance of buildings In Luxembourg, the energy performance certificate (CPE) rates homes from A+ to I; the European A–G scale has not yet been transposed.
EN 15316 Method for calculating heating demand Calculation of the heating system’s annual energy use (heat pump included). Sizing the heat pump itself relies on the heat-loss calculation to EN 12831.

Minimum efficiency requirements in 2026 (Luxembourg)

  • Klimabonus conditions: COP ≥ 3.1 (A7/W35) for an air-to-water heat pump; COP ≥ 4.3 (B0/W35) for a ground-source heat pump; no grant for an air-to-air heat pump
  • Minimum SEER (cooling): 4.6 legal minimum for units under 6 kW (Regulation (EU) 206/2012); aim for 6 or more
  • Energy class: Luxembourg’s CPE runs from A+ to I (European A–G scale not transposed)
  • Noise limit: set by municipal regulations (model regulation: 40 dB(A) at the neighbouring plot boundary)

Mandatory technical documents to obtain

Document Content How long to keep it
SCOP/SEER data sheet Certified to EN 14825. Exact SCOP/SEER of the model ordered. Reference climate conditions. At least 5 years
Energy performance report Annual energy calculation, energy performance class assigned, savings compared with the old heating system. With the deed of sale if you sell
Certificate of compliance with standards Signed by the installer: installation complies with EN 14825, EN 378, EN 12102-1 and EU directives. At least 10 years
Installation certificate Heat pump serial no., refrigerant quantity, leak tests, date, signature of the F-gas certified installer, Chambre des Métiers no. At least 10 years
Manufacturer’s manuals User, maintenance and troubleshooting manuals. After-sales service contacts. Keep with the heat pump
Manufacturer’s warranty Terms, duration (minimum 2 years on parts, 5 years on the compressor), manufacturer’s after-sales contacts. For as long as the warranty is valid
Invoice for labour + equipment Full description, price, VAT. Proof of legal purchase, consumer rights. At least 5 years
Consumer rights

Keep the invoice, the installation certificate and the compliance documents for at least 5 years. If a fault or breakdown is covered by the warranty, these documents are essential to assert your rights (replacement, free repair).

Heat pump rules in co-owned buildings (condominiums)

Installing a heat pump in a co-owned building means following additional procedures laid down by the amended law of 16 May 1975 on co-ownership, supplemented by specific municipal regulations.

Classification: private parts vs common parts

Location Status Required procedure
Private balcony/terrace, private garden, inside the flat Private part ⚠ General meeting vote if the unit alters the building’s external appearance (art. 16 b); otherwise free to install — notifying the property manager (syndic) recommended (30 days)
Visible façade of the building, shared roof, courtyard/driveway, shared car park Common part ✗ General meeting vote mandatory

Procedure for common parts (façade, roof)

  1. Written request to the syndic (30 days beforehand): full presentation of the project, detailed quote, accurate plans, acoustic study where applicable
  2. Review by the syndic: check of planning compliance and the appearance of the façade
  3. Submission to the general meeting: mandatory vote by a majority of the votes of all co-owners (Art. 16 of the law of 16 May 1975; see co-ownership voting rules)
  4. Written approval: decision recorded in signed minutes
  5. Carrying out the work: only once the vote has been passed
Situation Right/obligation Details
Private balcony Right to install General meeting vote required if the unit alters the building’s external appearance (art. 16 b); otherwise, notify the syndic for information. You bear 100% of the costs and maintenance.
Shared façade Approval required General meeting vote mandatory. May be refused (appearance, noise, common interest).
Maintenance Full responsibility The heat pump is your property. Annual servicing and replacement parts are at your expense.
Nuisance (noise) Legal liability You are liable for damage to neighbours if the heat pump exceeds the noise standards.
Condensate water Responsible management Water must drain away properly, not onto the façade or a neighbour’s home. The installer must deal with the pipework.
Co-ownership tip

Even on a private balcony, notify the syndic in writing 30 days beforehand. This shows good faith, avoids surprises and makes approval easier if a vote is needed later on (particularly when selling).

Distances and liability towards neighbours

Legal liability towards neighbours is a key aspect of installing a heat pump in Luxembourg. Failing to respect minimum distances and noise standards exposes you to significant legal risks.

Mandatory minimum distances

Minimum distance Measured from Legal basis Technical reason
2 m (air-to-water heat pump) The neighbour’s property boundary (boundary line) Municipal building regulation (2023 model regulation) Setback laid down in the model regulation (exemption possible with an expert’s certificate); noise limited to 40 dB(A) at the neighbouring plot boundary
0.5 m Projecting elements (neighbour’s balconies, pipes, gutters) Local planning codes + building safety Prevents encroachment on the neighbouring structure and condensate water damage
1 m Clearance in front of the fan grille (warm air outlet) Manufacturer’s instructions Lets air flow freely and prevents recirculation (10–20% drop in COP)
0.3–0.5 m Sides of the outdoor unit Manufacturer’s specifications Maintenance access (cleaning the condenser, replacing the fan)

Legal liabilities explained

Excessive noise — civil liability. If the heat pump exceeds the noise standards (40 dB(A) at the neighbouring plot boundary under the model municipal regulation), your neighbour can take legal action for ‘abnormal neighbourhood nuisance’ (trouble anormal du voisinage) and demand that the installation be brought into compliance (adding anti-vibration mounts or an acoustic screen, or replacing the heat pump = €1,000–2,500 or more). The court can order you to pay damages (usually €500–5,000 depending on severity).

Vibration — isolation required. The compressor produces mechanical vibration that is transmitted to the building structure. The installer must fit anti-vibration mounts (rubber feet/springs) that reduce vibration by 80–90%. Ask for confirmation that these mounts have actually been fitted.

Condensate water — liability for damage. The condensate pipe must be connected to a gully or drain. It must never discharge onto the neighbouring property. If water runs towards your neighbour’s foundations or cellar and causes damage, you are liable for the repairs.

How to prevent disputes with neighbours

  1. Inform your neighbours: a friendly letter describing the heat pump project, the work schedule (usually 3–5 days) and your commitment to meeting the noise standards
  2. Have a prior acoustic study carried out: if the unit is < 3 m from neighbouring properties. It costs €500–800, but shows your commitment to compliance
  3. Share the study results: show that the heat pump will comply with the 40 dB(A) limit at the neighbouring plot boundary (e.g. a certified ‘low-noise’ model rated at 35 dB at 1 m)
  4. Get it written into the quote: the installer’s commitment on the sound power level of the outdoor unit, measured to EN 12102-1 (Klimabonus thresholds: 48, 51 or 55 dB(A) depending on output). The installer is then liable if this is exceeded.
Legal protection

An acoustic study BEFORE installation is the best legal protection. It shows your intention to follow good practice, provides proof of compliance and serves as documentation in the event of a future dispute. Its preventive cost (€500–800) is far lower than the cost of urgent compliance work (€1,500–2,500) and legal disputes (€2,000–5,000+ in lawyers’ fees).

Frequently asked questions about heat pump regulations

Do I need a permit before installing a heat pump?

It depends on the municipality and the type of installation. Unit on a private balcony with no structural alterations = generally not required. Unit on a visible façade = municipal authorisation usually required. Installation on the common parts of a co-owned building = permit + general meeting vote. Always contact the town hall before starting work. There is no general statutory deadline: if there is no reply within 3 months, the application can be deemed refused.

What happens if I don’t comply with noise standards?

The risks are serious: your neighbour can demand that the installation be brought into compliance (fitting anti-vibration mounts or an acoustic screen, replacing it with a quieter heat pump = €1,000–2,500 minimum), take legal action for damages, or invoke abnormal neighbourhood nuisance (court ruling, possible fines under the municipal police regulation). The best prevention is still an acoustic study BEFORE final installation (€500–800).

Is the installer responsible for legal compliance?

The certified installer is responsible for carrying out the work in line with technical standards (EN 14825, EN 378, F-gas). But you, as the owner, bear ultimate responsibility: it is up to you to make sure the permit has been obtained, the installer is certified and the standards are met. If there is a defect, you can take the installer to court for non-compliance.

Can I install a heat pump myself (DIY)?

No, this is strictly prohibited. Only an F-gas certified professional (Category I, or Category II for equipment containing less than 3 kg of refrigerant) is authorised to handle refrigerants, charge the system and carry out leak tests. DIY risks: a fine, a heat pump that does not work, an F-gas leak into the environment, no warranty rights whatsoever and no insurance cover. A DIY installation is legally invalid.

How long should I keep the installation certificate?

Keeping it for at least 10 years is recommended: it proves legal compliance in the event of a dispute, allows future maintenance and is essential if you sell your home (give a copy to the buyer). Keep it with your property documents.

How can I check whether my installer is genuinely certified?

Go to www.cdm.lu (Chambre des Métiers Luxembourg), section ‘Contrôle installations bâtiment’, and enter the company name or registration number. An ‘actif’ (active) status confirms registration. Then ask for: 1) a copy of a valid F-gas certificate (check the expiry date), 2) a public liability insurance certificate (€500k minimum), 3) a signed quote showing the registration number. Without these documents, do not commit to anything.

Is my old R410A heat pump still legal in 2026?

Yes, an existing R410A installation remains legal for normal operation in 2026 and beyond. It can also still be serviced and topped up: since 1 January 2026, Regulation (EU) 2024/573 has only banned servicing with virgin refrigerants with a GWP of 2,500 or more, and R410A (GWP 2,088) is below that threshold. The gradual HFC quota phase-down will, however, make this refrigerant scarcer and more expensive: when you replace the unit, choose one running on R290 or another low-GWP refrigerant.

In a co-owned building, can I install a heat pump without the syndic’s approval?

Only if the unit stays out of sight: on a balcony or other PRIVATE part, a general meeting vote is required as soon as the outdoor unit alters the building’s external appearance (art. 16 b of the law of 16 May 1975). No, if the installation affects the SHARED façade or roof (a general meeting vote is mandatory, and the request may be refused). Good practice: notify the syndic in writing 30 days beforehand, even for a private part. The application put to the vote must include plans, an acoustic study, proof of the installer’s insurance and your undertaking to bear the costs.

How much does a heat pump installation that complies with Luxembourg regulations cost?

Air-to-air heat pump: €6,000–10,000 (supply and installation). Air-to-water heat pump: €12,000–24,000. Ground-source, including drilling: €25,000–45,000. Additional compliance-related costs: municipal permit (€0–300), acoustic study (€500–800), anti-vibration mounts/screen if noise is an issue (€400–2,500). The Klimabonus pays flat-rate grants: €10,000 for an air-to-water heat pump replacing fossil-fuel or electric heating in a house (€12,000 if ordered before 30 June 2027) and €12,000 for ground-source (€14,000); air-to-air heat pumps are not eligible. Ask for a detailed quote that includes all compliance costs.

Take action — estimate your grants and compare quotes

Use our simulator to find out exactly which grants you are entitled to, then request and compare several free quotes from verified installers in Luxembourg.

  • Guichet.lu — planning regulations and municipal authorisations in Luxembourg
  • Klima-Agence Luxembourg — technical conditions for heat pump installations and certifications 2026
  • Chambre des Métiers du Luxembourg — register of approved installers, F-gas certifications
  • Amended law of 21 June 1976 on combating noise — Legilux.public.lu
  • Regulation (EU) 2024/573 on fluorinated greenhouse gases — EUR-Lex
  • Standards EN 14825, EN 378, EN 12102-1 — CEN/CENELEC
The regulatory information is based on Luxembourg law and EU regulations in force in September 2026. For legal advice specific to your situation, consult a notary or a lawyer. Regulations may change. Always check with your local authorities before starting work.